Q.151.How do we compute the “Expected Value” for Software Size? • Ans. Expected value for estimation variable (size), S, can be compute as Weighted Average of Optimistic (opt) most likely (m), and Pessimistic (pess) estimates. • S = (opt + 4 m + pess ) / 6 Q.152. What is an Object Point? Ans. Object Point means: Count is determined by multiplying original number of object instances by weighting factor and summing to obtain total object point count. Q.153. List out the basic principles of software project scheduling? Ans . Basic Principles of Software Project Scheduling are: • Compartmentalization • Interdependency • Time Allocation ...